Võhma Wind

The Võhma wind farm is a planned wind farm in Türi municipality, next to the village of Võhma.

Status
In the planning stage
Location
Next to Võhma town
Height of wind turbines
250 m
Number of wind turbines
up to 3
Expected total production
Ca 51 GWh

Project Timeline

Year 1

Mapping

Suitable land areas and contacting landowners

Current phase

Year 1

Analysis

Further assessment of the wind farm location.

Year 2.

Initiate

Start the special planning process with the local municipality.

Year 2.

Environmental Impact Assessment

Commence the evaluation of environmental impacts.

Year 3.

Public Discussions

Hold initial public hearings and consultations.

Avala arvamust!

Year 3.

Refinement

Finalise planning following public discussions and impact assessments.

Year 4.

Plan Approval

Official adoption of the planning decision

Year 4.

Construction Begins

Wind farm construction starts and is expected to take 1–2 years.