Rudsvellhøgda Wind

Rudsvellhøgda wind farm is a planned onshore wind project in Nord-Odal, designed to harness strong local wind resources and deliver renewable power to nearby communities and industry.

Location
Rudsvellhøgda, Nord-Odal Municipality
Status
Planning
Turbines
5-6
Effect
36-43 MW
Production
Ca 110-132 GWh

Local contribution

Rudsvellhøgda wind farm will support local industry and value creation. The project can strengthen energy supply for businesses, create jobs during both construction and operation, and generate increased revenues for the local community.

The area has a single landowner. The municipality owns adjacent land that may be considered for expansion. In that case, the municipality would receive lease income as a landowner, in addition to the general revenues from wind power in the municipality, which today amount to around NOK 1 million per turbine per year.

Project timeline

2024

Project concept and land-owner agreements.

The project is being established in consultation with the landowner.

2025

Submission of planning initiative

Municipal processing and open office day

Current phase

2026

Planning and assessment programme

Planning and assessment programme established

Including hearing / public meetings.

2026 - 2027

Area plan and environmental impact assessment

environmental impact assessment developed in accordance with applicable guidelines

2028

License application

2028

Political consideration of area plan

2029

Licence processing

Licence processing by authorities; if needed, appeals processing.

2029

Complaint handling, if applicable

2029-2030

Contracting and project planning

Detailed design

2030

Construction phase

2031

Operation begins