Rudskogen Wind

The project is located south of Rudskogen Motorsenter in Sarpsborg municipality. It includes three planned turbines of 7.2 MW each, with an expected annual production of around 65 GWh. The wind farm will be able to supply the equivalent of approximately 4,300 households.

Location
Rudskogen, Sarpsborg Municipality
Status
Planning and assessment program
Turbines
3
Production
Ca 65 GWh
Effect
Inntil 22 MW
Homes powered
4,300 homes

Local contribution

For Sarpsborg municipality, the wind farm will provide additional income through property tax, production fees, and a share of the resource rent tax, amounting to an estimated NOK 3 million annually.

New and upgraded grid infrastructure, together with new renewable power from the project, will help open opportunities for new industries to establish themselves locally.

The project will also create local ripple effects during both construction and operation, through the purchase of local and regional goods and services and through local personnel employed to operate the wind farm.

Project timeline

2025

Project concept and land-owner agreements

The project is being established in consultation with the landowner

2026

Planning and assessment program

Current phase

Including hearing / public meetings

2026 - 2027

Area plan and impact assessment

Area plan and environmental impact assessment developed in accordance with applicable guidelines

2028

License application

2028

Political consideration of area plan

2029

License processing

Licence processing by authorities; if needed, appeals processing

2029

Complaint handling, if applicable

2029-2031

Contracting and project planning

Detailed design

2031 – 2032

Construction phase

2032

Operation begins