Rudskogen Wind
The project is located south of Rudskogen Motorsenter in Sarpsborg municipality. It includes three planned turbines of 7.2 MW each, with an expected annual production of around 65 GWh. The wind farm will be able to supply the equivalent of approximately 4,300 households.
-
Location
- Rudskogen, Sarpsborg Municipality
-
Status
- Planning and assessment program
-
Turbines
- 3
-
Production
- Ca 65 GWh
-
Effect
- Inntil 22 MW
-
Homes powered
- 4,300 homes
Local contribution
For Sarpsborg municipality, the wind farm will provide additional income through property tax, production fees, and a share of the resource rent tax, amounting to an estimated NOK 3 million annually.
New and upgraded grid infrastructure, together with new renewable power from the project, will help open opportunities for new industries to establish themselves locally.
The project will also create local ripple effects during both construction and operation, through the purchase of local and regional goods and services and through local personnel employed to operate the wind farm.
Project timeline
2025
Project concept and land-owner agreements
The project is being established in consultation with the landowner
2026
Planning and assessment program
Including hearing / public meetings
2026 - 2027
Area plan and impact assessment
Area plan and environmental impact assessment developed in accordance with applicable guidelines
2028
License application
2028
Political consideration of area plan
2029
License processing
Licence processing by authorities; if needed, appeals processing
2029
Complaint handling, if applicable
2029-2031
Contracting and project planning
Detailed design
2031 – 2032
Construction phase
2032
Operation begins