Nupberget Wind

Nupberget wind power plant is planned in Elverum municipality. The area is located on Nupberget, a prominent ridge northeast of Elverum town center, between Glomma and Osensjøen. The project consists of seven wind turbines with a total installed capacity of up to 50 MW, and an expected annual production of approximately 160 GWh.

Location
Elverum Municipality
Status
Under development
Turbines
7
Production
Ca 160 GWh
Installed capacity
Up to 50 MW
Height
Up to 270 m total height

Local Collaboration and Impact

The establishment of Nupberget wind power plant will provide Elverum municipality with increased revenue in the form of property tax from the power plant and production tax. This will strengthen the municipality’s economy and contribute to more flexibility in the local community.

The goal of the project is to utilize the good potential for energy production in the area. Nupberget is located in an area with stable and good wind conditions and little development nearby.

The development will also facilitate local business development. New power production and upgrading of existing grid provide better conditions for establishing new industry and jobs in the region.

In addition, the project will create local ripple effects both during construction and operation, through purchases of goods and services from local and regional suppliers, as well as jobs related to operation and maintenance.

Project area

Project timeline

2024

Project concept and land-owner agreements.

The project is being established in consultation with the landowner.

2025

Submission of planning initiative

Municipal processing and open office day

Current phase

2026

Planning and assessment programme

Planning and assessment programme established

Including hearing / public meetings.

2026 - 2027

Area plan and environmental impact assessment

environmental impact assessment developed in accordance with applicable guidelines

2028

License application

2028

Political consideration of area plan

2029

Licence processing

Licence processing by authorities; if needed, appeals processing.

2029

Complaint handling, if applicable

2029-2030

Contracting and project planning

Detailed design

2030

Construction phase

2031

Operation begins