Gilderåsen Wind

A planned wind power plant east of Elverum municipality. The project is planned with 8-12 turbines, with an installed capacity of up to 86.4 MW.

Location
Elverum Municipality
Status
Planning
Turbines
8-12
production
Ca 170 - 260 GWh
Installed capacity
57,6 - 86,4 MW
Height
Up to 270 m total height
Homes powered
17.000

Local Collaboration and Impact

The establishment of Gilderåsen Wind Power Plant can provide Elverum municipality with increased revenue through property tax and fees related to power production. This will strengthen the municipal economy and give the local community greater economic freedom.

The project’s purpose is to utilize the area’s good wind resources for renewable energy production.

Such development could promote business in the region. New power production combined with improved power grid will create more favorable conditions for new establishments in industry and more local jobs.

In addition, such a project could generate positive economic effects in the area both during the construction phase and during operation, including by using local and regional companies as suppliers of goods and services, as well as through employment in connection with the operation and maintenance of the facility.

Preliminary plans show the possibility of up to 8-12 turbines, but the final number will be determined later in the process. During the planning phase, the framework for where the wind power plant can be built and which areas can be used is established. The final size of the development and technical details are determined first in the concession phase, when the project is to be assessed and approved by the municipality.

Project timeline

2024

Project concept and land-owner agreements.

The project is being established in consultation with the landowner.

2025

Submission of planning initiative

Municipal processing and open office day

Current phase

2026

Planning and assessment programme

Planning and assessment programme established

Including hearing / public meetings.

2026 - 2027

Area plan and environmental impact assessment

environmental impact assessment developed in accordance with applicable guidelines

2028

License application

2028

Political consideration of area plan

2029

Licence processing

Licence processing by authorities; if needed, appeals processing.

2029

Complaint handling, if applicable

2029-2030

Contracting and project planning

Detailed design

2030

Construction phase

2031

Operation begins

Project boundary alternatives

Planområde alternativ 1
Planområde alternativ 2