Gilderåsen Wind
A planned wind power plant east of Elverum municipality. The project is planned with 8-12 turbines, with an installed capacity of up to 86.4 MW.
-
Location
- Elverum Municipality
-
Status
- Planning
-
Turbines
- 8-12
-
production
- Ca 170 - 260 GWh
-
Installed capacity
- 57,6 - 86,4 MW
-
Height
- Up to 270 m total height
-
Homes powered
- 17.000
Local Collaboration and Impact
The establishment of Gilderåsen Wind Power Plant can provide Elverum municipality with increased revenue through property tax and fees related to power production. This will strengthen the municipal economy and give the local community greater economic freedom.
The project’s purpose is to utilize the area’s good wind resources for renewable energy production.
Such development could promote business in the region. New power production combined with improved power grid will create more favorable conditions for new establishments in industry and more local jobs.
In addition, such a project could generate positive economic effects in the area both during the construction phase and during operation, including by using local and regional companies as suppliers of goods and services, as well as through employment in connection with the operation and maintenance of the facility.
Preliminary plans show the possibility of up to 8-12 turbines, but the final number will be determined later in the process. During the planning phase, the framework for where the wind power plant can be built and which areas can be used is established. The final size of the development and technical details are determined first in the concession phase, when the project is to be assessed and approved by the municipality.
Project timeline
2024
Project concept and land-owner agreements.
The project is being established in consultation with the landowner.
2025
Submission of planning initiative
Municipal processing and open office day
2026
Planning and assessment programme
Planning and assessment programme established
Including hearing / public meetings.
2026 - 2027
Area plan and environmental impact assessment
environmental impact assessment developed in accordance with applicable guidelines
2028
License application
2028
Political consideration of area plan
2029
Licence processing
Licence processing by authorities; if needed, appeals processing.
2029
Complaint handling, if applicable
2029-2030
Contracting and project planning
Detailed design
2030
Construction phase
2031
Operation begins